Why December needs a plan
For many product businesses, December is the biggest month of the year: gifts, end-of-year events and family visits push sales well above a normal month. At the same time suppliers, printers and transporters are at their busiest, so everything takes longer to arrive.
Running out in the second week of December costs you the sales you planned the whole year for, so plan now, while there's still time to order.
Step 1: estimate December's sales
Start from last December, not an average month, and adjust it for how the business has grown.
A skincare brand in Accra sold 1,800 jars of body butter last December, against about 900 in a normal month. Sales this year are running about 25% higher, so they plan for 2,250 jars this December.
Step 2: take away what you already have
Count what's in stock and what's already on the way, then order only the difference.
Body butter, 200 ml
- Expected December sales (1,800 + 25%)
- 2,250 jars
- Already in stock
- 600 jars
- Already being made
- 300 jars
- Still to make
- 1,350 jars
Step 3: work back from your lead times
Every material that goes into a jar has its own lead time, and in the busy season you should assume it will be longer than usual.
For the shea butter, 1,350 jars at 120 g a jar is 162 kg. The supplier usually delivers in 10 days, but in November plan for three weeks. To sell the extra jars through December, production has to start in mid-November, so the shea butter needs to be ordered by the end of October.
If your jars and lids come from abroad, order them first, as shipping takes longest. Labels and gift boxes need time too: printers book up early in the season, and a custom box can take weeks.
Step 4: protect your cash
Stocking up ties up money for weeks before customers pay. A few ways to keep it under control:
- Put most of the extra into the products that sold best last December.
- Split big orders into two deliveries, so the second can be changed if sales are slower.
- Ask suppliers early about payment terms for festive orders.
Planning it in Olonka
With the Planning add-on, the Plan page shows each product's and material's projected stock by day, week or month, and the first date it runs out. Switch on Include forecast demand to add expected sales on top of the orders you already have.
Where you know better than the forecast, such as a December rush, you can enter your own forecast demand for a period. Olonka marks it as manual and recalculates the projections, and you can reset it to the system forecast at any time.
The Replenishment tab then lists what will run short, with the missing quantity, a suggested quantity, the supplier, the estimated cost and a suggested order-by date. You can create the purchase order or manufacturing order from there.
Forecast demand entered by hand for one week in Olonka.
Common mistakes
- Planning from a normal month. December can be double an ordinary month or more, so use last December's figures.
- Ordering products but not packaging. Jars, labels and boxes run out too, and they often take longest to replace.
- Assuming usual lead times. Suppliers and transporters are slower in the busy season, so add time.
- Leaving it until December, when the only stock you can get is what's already on the shelf.
Once the rush is over, set sensible reorder points so January's orders come in on time without overstocking.