What lead time includes
A supplier's lead time is how long you wait between placing an order and having the goods on your shelf, ready to use or sell. Count it door to door. It includes:
- The supplier getting the order ready: making it, packing it, or waiting for their own stock.
- Any wait for your payment or a deposit before they dispatch.
- Transport, and for imports the time at the port and in customs.
- Receiving: unloading, checking the goods and putting them away.
It doesn't include the days before you place the order. That part is up to you, and it's what a reorder point is for.
Why the supplier's quote isn't enough
Most suppliers quote a lead time when you first buy from them, and it's usually their best case: the goods in stock, a truck free, no rain on the road. Real deliveries vary around it and are rarely faster.
The quote also leaves out your side. If goods sit at the gate for a day before anyone checks them in, that day is part of your lead time too. To know the real figure, measure it from your own orders.
How to measure it
For each order, you need two dates: the day you placed it and the day the goods were received.
Lead time = received date − order date
- Order date
- The day you sent the order to the supplier.
- Received date
- The day the goods were checked in and on the shelf.
Then look at the last six to ten orders from the same supplier:
- Count calendar days for each order, weekends included.
- Add them up and divide by the number of orders. The average is the lead time to plan with.
- Note the longest one: your worst normal case, which safety stock has to cover.
- Count how many orders arrived within the quoted time, for the supplier's on-time record.
Measure each supplier separately. Two suppliers of the same material can have very different lead times, and that's often a reason to choose one over the other.
A worked example
A skincare maker in Accra buys refined cocoa butter from a processor in Kumasi. The supplier quotes 7 days. The maker looks back at their last six orders:
Cocoa butter from a supplier in Kumasi, quoted at 7 days
- Ordered 1 June, received 9 June
- 8 days
- Ordered 22 June, received 1 July
- 9 days
- Ordered 13 July, received 20 July
- 7 days
- Ordered 3 August, received 15 August
- 12 days
- Ordered 24 August, received 1 September
- 8 days
- Ordered 14 September, received 24 September
- 10 days
- Average lead time (54 days ÷ 6 orders)
- 9 days
So the real lead time is 9 days, not 7. The slowest order took 12 days, and only one of the six arrived within the quoted 7.
What to do with the number
The maker uses about 15 kg of cocoa butter a day. Planned on the quoted 7 days, with 50 kg of safety stock, their reorder point was 15 × 7 + 50 = 155 kg.
On a normal 9-day wait they use 135 kg, so most orders ate 30 kg into the safety stock before the delivery came. On the 12-day order they needed 180 kg and had 155, so they ran out on the eleventh day.
On the measured 9 days, they use 15 × 9 = 135 kg while they wait. To cover the slowest delivery, they keep 15 × (12 − 9) = 45 kg spare, so they now reorder at 135 + 45 = 180 kg. If their daily use also jumps around, the safety stock guide shows how to cover busy days as well.
Supplier lead times in Olonka
Each supplier in Olonka has a Lead time (in days) on its General tab. When you choose the supplier on a new purchase order, Olonka sets the Expected date to the order date plus that lead time. For a supplier without one, it uses the default delivery time for purchase orders from Settings > General. You can still change the expected date on any order.
When the goods arrive and you receive them, Olonka records the day each line is first received, and the order shows its Received date. The supplier's Purchases tab lists their orders with the order date, expected date and received date side by side, and so does the Done tab of your purchase orders, so late deliveries are easy to spot.
The Reports page does the sums. Reports > Purchasing > Overview shows the Average lead time (days) for the period you choose, and the Suppliers report shows it for each supplier beside what you spent with them. It counts the days from each line's order date to the day it was first received, and leaves out lines not received yet and cancelled orders, so expected dates never mix with real ones. Enter that average as the supplier's lead time, and new orders get an expected date based on how the supplier really delivers.
With the Planning add-on, the lead time also tells you when to order: Suggested order by on the Planning page is the stockout date less the default supplier's lead time. More on purchasing in Olonka on the Buy page.
Common mistakes
- Planning on the supplier's quote leaves you short when deliveries run late. Use the average from your own orders, and keep checking it against the quote.
- Averaging away the slow deliveries hides your worst case. The average sets the reorder point and the longest delivery sets the safety stock, so keep both.
- Receiving goods days after they arrive makes your lead times look longer than they are. Check deliveries in the day they come.
- A lead time measured once goes out of date: it changes with the season, the roads and the supplier's other customers. Check it every quarter, and before a busy season such as December.